Bathroom Renovation Diary

The Old Bathroom

It's time for a face lift

hamilton_bathroom_renovation_day0.jpg


Day1 and 2 - Gutting the room

The garbage bin arrives, the room is stripped bare and the concrete floor is hammered away. The team vacuums the area and leaves the house clean and tidy.

hamilton_bathroom_renovation_day1.jpg

Day 3 - Plumbing

Moving the toilet and starting the wiring and plumbing for the in-floor heating

hamilton_bathroom_renovation_day3.jpg

Day 4 - Power and Boiler Connections

The 2nd floor bathroom is connected to the basement boiler (in-floor heating) and eletrical panel

hamilton_bathroom_renovation_day4.jpg

 

Day 5 - In-Floor Heating Cabling & Drywall

The sub-floor is down, the drywall is started, the in-floor heating cables are put in position awaiting the concrete

hamilton_bathroom_renovation_day5.jpg

Day 6 - Concrete Floor

We let it dry over the weekend.

hamilton_bathroom_renovation_day6.jpg

Day 7 - Finish the drywall

We are now ready for the tiles.

hamilton_bathroom_renovation_day7.jpg

Day 8 - The Tiles

We are beginning to see the finished room.

hamilton_bathroom_renovation_day8.jpg

Day 9 - The Painting

hamilton_bathroom_renovation_day9.jpg

Day 10 - Coming together

hamilton_bathroom_renovation_day10.jpg

Day 11 - The Finished Bathroom

Click here to view large panorama image